Crossroads icon with stick figure and bicycle and words 'crossroads with lights'

A4095 / B4100 Banbury Road roundabout improvements

We are converting the existing roundabout into a signalised junction with traffic lights to improve traffic flow and encourage more walking and cycling.

About the project

Image of the Banbury Road roundabout work

Confirmed design for construction

Bicester is one of the fastest-growing towns in Oxfordshire and the Banbury Road roundabout is a key junction along the Bicester ring road which was identified as a site for improvement in our Local Transport Plan.

The junction must be able to safely handle the number of vehicles travelling in the area, when new homes and jobs come to the town, and provide improved facilities that encourage more people to walk and cycle.

We are redeveloping this junction, and the work will:

  • convert the existing roundabout into a signalised junction better able to cope with increased traffic levels
  • improve safety for cyclists and pedestrians, with segregated cycleways and crossings at the western and southern arms of the redesigned junction
  • increase capacity, helping to address congestion
  • maintain access for drivers making a right turn from Fringford Road
  • incorporate a reduced speed limit of 30mph.

What you can expect

We are working in phases to remove the existing roundabout island and construct the improved junction.

Due to the project's complexity, any unexpected discoveries in the ground, and weather conditions, the timeline and details of this work may change.

Phase one and two have been completed.

Phase three

Dates Location Activity Day/night Traffic management Pedestrian and cyclists
22 July to 26 July A4095 Installing a traffic protection barrier Night work, 8pm to 6am No traffic management or diversion required. No change to access
22 July to 28 October Banbury Road Closing the southern side of Banbury Road, from the roundabout to Lodge Close 24 hours, 7 days a week Narrow lanes on the northern half of the road and traffic lights at the junction used to manage traffic. Traffic towards Bicester diverted both ways via the ring road. Fringford road reopened. Bridleway re-opened.

During the Banbury Road closure, our teams will be:

  • working to create a new island on Banbury Road south
  • installing a new central island adjacent to the Fringford Road and on the roundabout east and west approaches
  • completing the second half of the toucan crossing on the A4095
  • constructing new drainage and footways
  • and surfacing the Banbury Road south up to the roundabout approach splitter island.

We expect phase three to finish by the end of October, after which the Banbury Road will reopened to all road users.

Temporary traffic diversion route in place during phase three, from July to October 2024. Traffic towards Bicester will be diverted both ways using the ring road.

Traffic management plan with pedestrian and cyclist diversion route

Traffic management plan with pedestrian and cyclist diversion route indicated in green. Pedestrians will be diverted along the Banbury Road. The existing footpath will be maintained at a reduced width and with a barrier installed. Cyclists will be directed to follow the pedestrian diversion, with the cycle path width reduced in places to facilitate shared used with pedestrians. The bridleway will be reopened.

Bus diversion route (500 - Banbury – Bicester) with temporary bus-stops indicated in red. Buses will be diverted using the Buckingham Road, with two new temporary bus stops in each direction provided for the 500 bus route.

Phase four

Dates Location Activity Day/night Traffic management Pedestrian and cyclists
29 October to 31 January 2025 A4095 westbound Works associated with widening the northbound approach of the B4100  24 hours, 7 days a week Banbury Road re-opened to traffic. Narrow lanes in place.  Details to follow

Phase five

Dates Location Activity Day/night Traffic management Pedestrian and cyclists
3 February 2025 to 7 February 2025 B4100 Road closure, road surfacing Night time Diversion via B4100 up to B430 and onto the ring road Details to follow
3 February 2025 to 18 February 2025 Various locations Finishing and electrical works completed as required  Day time Localised traffic management Details to follow

How can I stay up to date?

This web page will be updated regularly.

We recommend signing up to our travel and transport bulletin

Satellite navigation systems (SAT-NAV) will display updates on road closures, which can help when planning journeys.

Traffic management arrangements are also available by visiting https://one.network/

Feedback

We continue to receive feedback and are now working on the following suggestions, with more updates to follow.
You asked us to... We...
Act on reports of traffic violations within the work area and take action on vegetation that needed clearing and potholes that needed fixing. Have logged these issues in Fix My Street.
Allow for safer crossing for pedestrians, especially children. Adjusted the phase timing of the traffic lights and put up caution children crossing and look both ways signs

Contact us

If you would like to get in touch, please email banburyroadroundabout@oxfordshire.gov.uk. or write to Oxfordshire County Council, County Hall, New Road, Oxford, OX1 1ND. You can also register your interest in receiving updates about the work.

How it is being funded

The work is fully funded by central government, with the Ministry of Housing, Communities and Local Government providing £5.5 million and £5.9m secured from the Growth Deal.  The money can only be used for this scheme.

More information

Why are these improvements needed?

With more than 6,000 new homes planned for the local area, data forecasting shows that the current roundabout will not be able to safely handle the volume of predicted vehicle traffic. The redesigned junction will improve safety for drivers, cyclists, and pedestrians by regulating traffic in a more structured way using signals and lower speed limits.

What will the new junction look like?

The existing roundabout will be converted into a signalised junction. We are adding segregated crossings and paths for pedestrians and cyclists at the western and southern arms and reducing the speed limit to 30 miles per hour.

Why does the speed limit need to reduce?

Due to the crossing and raised table included in the new design, it is a legal requirement to reduce the speed limit to 30 miles per hour.

Why are you trying to encourage more walking and cycling?

Encouraging more people to walk, cycle or take public transport if they can is a key ambition of our local transport and connectivity plan. The redesigned junction will have better pavements and cycle paths and safer crossings, to help us achieve this.

How did you decide on the design?

An online public consultation on the initial three design options was held from 19 March to 9 April 2021. You can read the findings of the consultation in full (pdf format, 3.5Mb).

A member-delegated decision was made to take option two and develop it into a signalised junction with additional provision for safe cycling.

Further changes were incorporated following a review of the scheme in 2022 and additional stakeholder engagement in 2023. The change of design was approved at a cabinet member delegated decision meeting in October 2023.

As we have worked on the design, we have used consultation and planning application feedback, technical assessments and data modelling, safety reports, and a cost review to inform our thinking. We also considered council policies.

Why was the design changed?

Emerging cost pressures led to a review of the scheme in 2022. The scope of the work changed, and we revisited the design to reflect this. The current design should save money and have a reduced impact on the surrounding land, while maintaining features such as segregated cycleways and crossings.

How is the current design different from the old design?

The current design increases the vehicular capacity of the junction to a similar level as options one and two from the original consultation, includes segregated cycleways and crossings that are an improvement on the existing provision, and has a reduced impact on the surrounding land, as we do not plan to widen the highway as much as originally planned. This avoids the potential requirement for compulsory purchase orders and expensive delays which could lead to funding expiring.

The design is compliant with guidance and two road safety audits have taken place.

What safety improvements will be made for cyclists?

Buffer zones between the cycle track and the carriageway have been incorporated on the north-western section which is a key area of vulnerability where traffic turns and where we expect most cyclists to travel.

The speed limit will also be reduced from 40mph to 30mph on all arms of the junction. 

When was planning permission granted?

Planning permission was granted in November 2021 for a signalised junction to replace the existing roundabout. We submitted a follow-up Section 73 application in 2023 to take into account the minor changes required.

What engagement have you done?

We have used consultation feedback, planning application feedback and conversations with community representatives to help us make decisions as we developed these improvements. 

In 2021 we held a public consultation on three options for the redesigned roundabout. Further engagement took place with members and a community cycling group, including a June 2021 meeting with councillors.

Throughout 2023, we met with local interest groups as we finalised the current design.

An engagement event to provide information on the scheme was held for residents on 4 October 2023 to:

  • provide residents with an update on the progress of the scheme’s design
  • to explain the rationale behind the decisions made along with results from the modelling that supported the decision to deliver a signalised junction over a roundabout
  • to explain how the construction phase will be delivered and how traffic will be managed during the works
  • and answer any queries they may have on the design and construction process

We held a second event on 28 February 2024 and a third on 11 July 2024 to provide information on:

  • the construction phases
  • traffic management used
  • and how we have responded to feedback and mitigated issues on site

We have also engaged with various disability and access groups, local horse-riding societies and some local businesses.

How will you mitigate the environmental impact in the area?

The construction will be delivered in line with a Section 61 agreement – a formal agreement about how the work and its impact will be managed – reached between Cherwell District Council, Oxfordshire County Council and our contractor.

Vibrations: We don’t expect vibration to have an impact. This was assessed through ground investigation works.

Traffic congestion: A traffic and pedestrian management plan was produced and reviewed as part of the planning process. Our contractor assessed and mitigated the risks associated with the movement of vehicles, large machinery, and pedestrians (both site workers and members of the public) around the site.

Light pollution: We plan to install enough temporary lights to ensure the safety of road users is not compromised. We will maintain existing lighting levels around the junction and will not increase the light levels at night. Any flood lights installed in the compound will be angled down to limit light pollution.

How will you mitigate noise and air pollution in the area?

We will ensure that all tools are fitted with silencers and additional machinery and equipment are positioned furthest away from areas where the public could be affected and behind noise barriers. Noise will be reduced through planning, quieter equipment, anti-vibration mounts, training, and communication of and with the workforce. In addition to this, a noise monitoring system will be used to evaluate how our activities affect the surroundings.

To mitigate dust and air pollution, we will choose pre-made construction materials to reduce on-site activities. We will also use dust suppression equipment during the work.

Will there be enough space for cyclists, people with pushchairs, and people using wheelchairs or mobility aids to pass through during construction?

Yes, barriers will provide and protect two metres of space during construction.