Witney active travel route
Proposals in Witney are being funded through OxLEP allocation of £1.4m along with proposals in Bicester.
Following engagement with residents and organisations in January and February 2020, final scheme designs have been agreed and works began in April 2021 and are anticipated to be largely complete by end of June 2021
A full report of the results of the consultation, including elements that have been deferred can be found here (link to be provided)
Summary of works
Summary of works being undertaken
- Upgrade the signalised crossing at Tower Hill to a toucan crossing to allow people cycling to cross the road.
- Shared footway/cycleway at Tower Hill and Five Ways Roundabout
- On-road advisory cycle lane along Corn Street and Langdale Gate
- Removal of approximately three car parking spaces at 146-152 Corn Street, which is on the north side near the Water Margin restaurant. This will be performed under an experimental traffic regulation order to allow for a 6 month consultation period and further review. All other parking arrangements at Corn Street will remain as they are at present.
- Shared footway/cycleway at Witan Way roundabout
- Minor improvements to Langel Common path and Church Lane
- Upgrade the signalised crossing at Oxford Hill to a toucan crossing to allow people cycling to cross the road.
- Minor improvements to the section of Madley Park path between Oxford Hill and Park View Court (not the whole route).
- 20mph speed limit throughout the route including Corn Street, Church Lane, and Madley Park.
Programme of works
Works are underway and the progress of works is detailed in the table below:
Scheme section | Anticipated Start date | Anticipated Completion date | Status |
---|---|---|---|
Witan Way Roundabout | 06/04/2021 | 30/04/2021 | Complete |
Oxford Hill | 10/05/2021 | 07/06/2021 | Complete |
Tower Hill | 19/04/2021 | 22/06/2021 | Complete |
Off-road cycle facility Witan Way to Church Lane and Oxford Hill to Courts Gardens | 08/06/2021 | 14/06/2021 | Complete |
Off-road facility Courts Gardens to Park View Court | 15/06/2021 | 28/06/2021 | Complete |
Corn Street (Holloway Road to Market Square) | 12/05/2021 | 25/05/2021 | Complete |
Corn Street (Five Ways Roundabout to Holloway Rd) | 08/06/2021 | 08/06/2021 | Complete |
Market Square | 09/06/2021 | 09/06/2021 | Complete |
Langdale Gate | 10/06/2021 | 10/06/2021 | Complete |
Woodbank | 11/06/2021 | 11/06/2021 | Complete |
20mph zones | 14/06/2021 | 14/06/2021 | |
Cycle signs | 15/06/2021 | 15/06/2021 | Complete |
More information