Local Transport Delivery Plan 2026/27 to 2029/30

Local Transport Delivery Plan 2026/27 to 2029/30

On 19 December 2025, the Department for Transport’s Director of Local Transport, Planning and Housing confirmed Oxfordshire County Council’s Local Transport Consolidated Funding Settlement.

Following the 2025 Spending Review and subsequent ministerial decisions, DfT allocated approximately £245.5 million* to Oxfordshire County Council. This comprises approximately £223.2 million* in capital funding for 2026/27 to 2029/30, and £22.3 million* in revenue funding for 2026/27 to 2028/29.

*The Department may adjust these funding amounts at its discretion.

Integrated Transport Fund (ITF)

From 2026/27, the settlement brings the following formula-based local transport funding streams together within the Integrated Transport Fund, giving the Council greater flexibility to use funding efficiently across transport programmes:

  • Highways Maintenance funding, CDEL
  • Active Travel funding, RDEL and CDEL
  • Local Electric Vehicle Infrastructure Capability Funding, RDEL
  • Local Transport Grant, RDEL and CDEL
  • Local Authority Bus Grant, CDEL

The ITF is expected to support local transport outcomes across all modes. This may include highway maintenance, walking, wheeling and cycling, buses, light rail, electric vehicle charging infrastructure and schemes that connect different forms of transport. It may also support behaviour-change programmes and build the Council’s capacity and capability to develop and deliver transport investment and policies.

Bus Services Fund (BSF)

The Bus Services Fund is separate from the Integrated Transport Fund, and funding cannot be transferred between the two. It comprises the Local Authority Bus Grant revenue allocation, any Bus Service Operators Grant devolved under the Bus Services Act 2025, and any further dedicated local-authority revenue funding for buses.

The BSF must support services and schemes where most of the benefits are received by bus passengers. It cannot be used for road schemes that increase general network capacity where the benefit to bus services is only incidental or secondary.

Local Transport Delivery Plan (LTDP)

A Local Transport Delivery Plan (LTDP) is the plan that sets out how a Local Transport Authority (LTA) will use its Department for Transport consolidated funding and what it expects to deliver with it over the funding period.

For Oxfordshire, the LTDP covers 2026/27 to 2029/30 and translates the funding settlement into a programme of named schemes, programmes, expenditure and milestones. The LTDP was approved by Cabinet in September 2026.

For transparency, the Council must publish its Local Transport Delivery Plan (LTDP) and update it each year with progress and changes.

DfT's Local Transport Consolidated Funding Settlement

Local Transport Delivery Plan (LTDP) - 2026/27 to 2029/30

Published: November 2026

Funding summaries

Revenue and capital allocations by mode.

Bus Service Fund revenue

Bus Service Fund (BSF) revenue allocations by mode and financial year
Mode 2026/27 2027/28 2028/29 Total
Bus £5,484,810 £5,132,300 £5,132,300 £15,749,410

Integrated Transport Fund revenue

Integrated Transport Fund (ITF) revenue allocations by mode and financial year
Mode 2026/27 2027/28 2028/29 Total
Active travel £1,268,447 £1,100,000 £1,221,700 £3,590,147
'Back office' £604,000 £772,400 £650,700 £2,027,100
Electric vehicles and infrastructure £325,335 £325,335 £325,335 £976,005

Total revenue: £15,749,410 (BSF) + £6,593,252 (ITF) = £22,342,662

Integrated Transport Fund capital

Integrated Transport Fund (ITF) capital allocations by mode and financial year
Mode 2026/27 2027/28 2028/29 2029/30 Total
Active travel £3,590,500 £4,629,300 £7,014,700 £8,205,100 £23,439,600
Bus £3,247,000 £4,812,300 £5,377,600 £5,942,800 £19,379,700
Motor traffic including highways asset £34,635,000 £40,185,000 £43,430,000 £49,650,000 £167,900,000
Multimodal £4,494,000 £3,195,000 £2,250,000 £2,500,000 £12,439,000

Total capital: £223,158,300

Total Local Transport Consolidated Funding Settlement (revenue and capital): £245,500,962

Milestones

Scheme and programme development and delivery.

Revenue - bus

Bus milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Asylum seekers bus pass scheme Delivery only N/A N/A Sep 2026 Mar 2029
Continued support for enhanced local bus services Development and delivery Apr 2026 Jun 2026 Apr 2026 Mar 2029
Maintenance of the expanded RTPI screen asset base Delivery only N/A N/A Apr 2026 Mar 2029
MyBus Oxfordshire ticketing scheme Delivery only N/A N/A Apr 2026 Mar 2029
New local bus service support Delivery only N/A N/A Apr 2026 Mar 2029
Staff resources to support Bus Delivery Plan and EP activities Delivery only N/A N/A Apr 2026 Mar 2029
Transport Focus Your Bus Journey Survey Development and delivery Apr 2026 Jun 2028 May 2026 Mar 2029

Revenue - active travel

Active travel milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Active travel infrastructure full audit and mapping Development only Apr 2027 Mar 2029 N/A N/A
Active travel scheme development and feasibility Development only Sep 2026 Mar 2029 N/A N/A
Active travel training annual budget (officer attendance at conferences, accommodation, admin costs, etc.) Development only Apr 2026 Mar 2029 N/A N/A
Betterpoints Application Delivery only N/A N/A Apr 2026 Mar 2029
Bike Loan Scheme Delivery only N/A N/A Apr 2026 Mar 2029
Community Outreach Active Travel (COATs) Programme Delivery only N/A N/A Apr 2026 Mar 2029
Cycle interventions/workplace support Delivery only N/A N/A Apr 2026 Mar 2029
LCWIP development - Heyford Park Development only Apr 2027 Mar 2028 N/A N/A
LCWIP development - Eastern Oxfordshire (Watlington) Development only Apr 2026 Mar 2027 N/A N/A
LCWIP development - Henley Development only Oct 2026 Mar 2027 N/A N/A
LCWIP development - South East Oxfordshire (Goring Gap) Development only Oct 2026 Mar 2027 N/A N/A
LCWIP development - Western Vale (Faringdon Area) Development only Oct 2026 Jun 2027 N/A N/A
Ongoing British Cycling Officers Delivery only N/A N/A Apr 2026 Mar 2029
Ongoing School Engagement Officer Delivery only N/A N/A Apr 2026 Mar 2029
Oxford cordon survey annual budget Development only Apr 2026 Mar 2029 N/A N/A
School Travel Interventions/SSTS Delivery only N/A N/A Apr 2026 Mar 2029
Third School Engagement Officer Delivery only N/A N/A Apr 2026 Mar 2029
Training programme for OCC officers, councillors and stakeholders Development only Sep 2026 Mar 2029 N/A N/A
Workplace Technical Lead (Active Travel) Delivery only N/A N/A Apr 2028 Mar 2029

Revenue - 'back office'

'Back office' milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Implement Behaviour Change Strategy Delivery only N/A N/A Apr 2027 Mar 2029
ITF administration annual budget Development only Apr 2026 Mar 2029 N/A N/A
LTCP Supporting Policy Documents and Modelling Scenario Testing Development only Apr 2026 Mar 2029 N/A N/A
Quantified Carbon Assessment and Integrations Development and delivery May 2026 Mar 2028 Oct 2026 Mar 2029
Transport Modelling, Monitoring and Evaluation Development only Apr 2026 Mar 2029 N/A N/A

Revenue - LEVI

LEVI milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Oxfordshire EV Infrastructure Strategy (OEVIS) - updates Development only May 2026 Mar 2027 N/A N/A
OxLEVI Communications Development and delivery Jan 2026 Jul 2028 Nov 2026 Jul 2028
OxLEVI Programme Delivery Support Development and delivery Jan 2026 Jul 2028 Nov 2026 Jul 2028

Capital - active travel

Active travel milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Active travel minor improvements annual budget Development and delivery Sep 2026 Dec 2027 Jan 2028 Mar 2030
Ambrosden to Bicester Active Travel Scheme (Phase 2 and 3) Development and delivery Apr 2026 Oct 2027 Nov 2027 Aug 2028
Banbury Market Place Development and delivery Nov 2026 Jan 2027 Feb 2027 Jul 2027
Bicester Central Triangle Development and delivery Oct 2026 Mar 2028 Apr 2028 Mar 2030
Central Oxfordshire Cycle and micromobility parking Development and delivery May 2026 Dec 2026 Jan 2027 Jan 2028
Countywide Cycle Network Signage/Wayfinding Development and delivery Apr 2027 Mar 2028 Apr 2028 Mar 2030
East Oxford Active Neighbourhood Development and delivery Oct 2024 Feb 2027 Mar 2027 Jan 2028
Kelaart's Field Cycleway Extension Development and delivery Nov 2026 Mar 2027 Apr 2029 Mar 2030
Kidlington Green Road Improvements Development and delivery Oct 2026 Mar 2028 Apr 2028 Mar 2029
Middleton Stoney Road Active Travel Scheme Development and delivery Apr 2026 Dec 2026 Jan 2027 Nov 2027
Old Hungerford Road (SVATN Route 4) Development and delivery Sep 2026 Mar 2027 Apr 2028 Mar 2029
Oxford Junction Improvements (design only - Abingdon Road/Weirs Lane, Banbury Road/Marston Ferry Road, Banbury Road/Parks Road, London Place) Development only Apr 2027 Mar 2030 N/A N/A
Oxford Ring Road - Wolvercote Roundabout Development and delivery Sep 2026 Jun 2027 Oct 2027 Mar 2028
Path East of Sutton Courtney (Coordination with BT works HIF 1 connection) Delivery only N/A N/A Aug 2026 Mar 2027
Quiet Lanes Pilot Programme Development and delivery Apr 2026 Dec 2026 Sep 2026 Mar 2027
School Streets Phase 4 / Creating Safer routes to school 2027/28 Development and delivery Apr 2027 Sep 2027 Oct 2027 Mar 2028
School Streets Phase 5 / Creating safer routes to school 2028/29 Development and delivery Apr 2028 Sep 2028 Oct 2028 Mar 2029
School Streets Phase 6 / Creating safer routes to school 2029/30 Development and delivery Apr 2029 Sep 2029 Oct 2029 Mar 2030
Thame to Haddenham Active Travel Link Development only Apr 2026 Feb 2027 N/A N/A

Capital - bus

Bus milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Bus Enhanced Partnership Plus delivery including decarbonisation and ticketing Development and delivery Dec 2026 Sep 2029 Jun 2027 Mar 2030
Bus Priority Infrastructure and Improvements (various) Development and delivery Jan 2027 Sep 2029 Jun 2027 Mar 2030
Bus Stop and Transport hub Infrastructure Improvements Development and delivery Jan 2027 Sep 2029 Apr 2027 Mar 2030
Bus Vehicle Improvement Fund Development and delivery Apr 2026 May 2029 Jun 2026 Mar 2030
Real Time Passenger Information Displays Delivery only N/A N/A Apr 2026 Mar 2030
Traffic Signal Bus Priority Development and delivery Apr 2026 Sep 2029 Apr 2026 Mar 2030

Capital - motor traffic including highways asset

Motor traffic including highways asset milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Structural Maintenance Programme Delivery only N/A N/A Apr 2026 Mar 2030

Capital - multimodal

Multimodal milestones
Scheme or programme Delivery type Development start Development end Delivery start Delivery end
Benson Mobility Hub Development and delivery Jan 2026 Nov 2026 Dec 2026 Dec 2028
Didcot Central Corridor Development only Nov 2026 Jun 2027 N/A N/A
Heavy Goods (Pilot Interventions) - Henley Town Centre Improvements and Windrush Valley Delivery only N/A N/A Sep 2027 Mar 2028
Henley Town Centre Improvements Development only Nov 2026 Jul 2027 N/A N/A
St Giles and Broad Street Improvements Development and delivery Apr 2026 Dec 2026 Jan 2027 Mar 2027
Vision Zero Programme (including A&RS) Development and delivery Apr 2026 Mar 2030 Apr 2026 Mar 2030
Wantage Market Place Regeneration Development and delivery Apr 2026 Aug 2027 Sep 2027 Mar 2028
Witney Fiveways Roundabout (Design only) Development only Apr 2028 Mar 2030 N/A N/A

Notes

“N/A” means not applicable, as shown in the source document.