This scheme will construct new west-facing slip roads at the A40/B4022 Shores Green junction to improve access to Witney.

Planned overnight road closures and works

A programme of overnight highway works is currently scheduled to take place between April and May 2026. Please note that all dates and works listed below are subject to change. Residents and road users are advised to check our website regularly for the latest information and any updates to the programme.

From 7 April 2026 for nine nights

Overnight resurfacing works will be carried out on the B4022.

  • the B4022 will be closed throughout the works
  • both the on-slip and off-slip roads will also be closed
  • signed diversion routes will be in place

From 20 April 2026 for three nights

Resurfacing works will take place on the A40.

  • the A40 will be closed overnight in both eastbound and westbound directions

From 23 April 2026 for two nights

Finish any remaining resurfacing work and associated white lining on the B4022.

  • the B4022, including the on-slip and off-slip roads, will be closed overnight
  • final details of these works are to be confirmed

From 4 May 2026 for five nights

Overnight closures will be required to allow for signage installation and vegetation clearance.

  • the A40 eastbound will be closed between Downs Road Roundabout and Ducklington Roundabout
  • access will be managed via signed diversion routes

From 11 May 2026 for five nights

Further overnight works will be carried out to install road markings, including the centre line, extending beyond the current site limits.

  • the A40 will be closed in both directions between the Oxford Hill slip roads and Hill Farm
  • diversions will be clearly signed throughout the closure period

Fig 1 - Traffic Management Plan for A40 closure 

Ongoing restrictions 

From 5 January 2026 to 30 April 2026, new temporary traffic signals and pedestrian diversions will be in place as follows:

  • 3-Way Traffic Lights: Temporary signals will be positioned on the B4022 (just south of the bridge), on South Leigh Road, and at the end of the westbound off-slip.
  • Bus Stop Relocation: The current bus stop will be temporarily moved. A new stop will be installed approximately 75 metres from the existing one.

Pedestrian Access: For pedestrians, a dedicated pedestrian route will be maintained through the works area

From 10 February 2025 until the end of construction, 

  • the speed limit on the A40 within the scheme extents will be temporarily reduced to 50mph and the B4022 within the Scheme extents will also be temporarily reduced to 30mph.
  • Lane 1 of the A40 within this project area will be closed in both directions. Other lanes will remain open to traffic.

Appropriate traffic signs are displayed to indicate when traffic measures are in force. The alternative route for traffic affected by any closure is via signed diversion route.

Any major construction project that modifies an existing highway will cause disruption. We are doing all we can to mitigate disruption to the greatest extent possible through phased implementation and speed limit reductions for the safety of our road network users and our workforce. We appreciate your patience as these improvements are carried out.