Guidance document Delivery Plan: Science Vale - Movement and Place Plan
Both the costs and delivery timescales are indicative only at this point, and are likely to change as the plans for each action develop further and projects start to be delivered. The delivery timescales are from when the project or action commences, as opposed to committing us to a specific delivery time frame at this stage.
| Number | Action | Estimated Cost | Delivery timescale |
| 1.1 |
Investigate options for the development of schemes for improved public realm, walking, wheeling, cycling, and public transport in:
|
Over £500k | More than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 2.1 | Create a sense of togetherness, place, inclusiveness, and community in new and existing places. | Between £100k and £500k | Between 2 and 5 years |
| 2.2 | Collaborate with partners to support accessible new or enhanced wayfinding, and introduce murals, artwork, rest places, pocket parks, and community parks | Less than £100k | Less than 2 years |
| 2.3 | Work with partners to enhance and upgrade timetables (for buses, activities and events), local guides, maps etc which showcase the local area and its history | Less than £100k | Less than 2 years |
| 2.4 | Support the district councils when they update their Joint Design Guide | Less than £100k | Less than 2 years |
| 2.5 | Seek opportunities to address sub-standard crossing points (including dropped kerbs and tactile paving) to support accessibility and inclusivity | Between £100k and £500k | Less than 2 years |
| 2.6 | Work with partner to remove or improve access control barriers to support accessibility and inclusivity in accordance with our Access Control Barrier Policy | Less than £100k | Less than 2 years |
| 2.7 | Investigate opportunities to develop the 'Oxfordshire Way' and Community Hubs | Between £100k and £500k | More than 2 years |
| 2.8 | Work with partners with a view to provide more community hubs and mixed-use hubs | Between £100k and £500k | Up to 5 years |
| 2.9 | Support opportunities to provide multi-use leisure destinations (e.g. bars/cafés with a range of leisure facilities), in sustainable locations | Between £100k and £500k | Between 2 and 5 years |
| 2.10 | Liaison with workplaces, stakeholders, and partners to join different employment groups together to share ideas and best practice | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 3.1 | Work with partners to deliver the walking, wheeling and cycling schemes contained within adopted documents (such as the LCWIP and SATN routes). | More than £500k | More than 2 years |
| 3.2 | Finalise and adopt the LCWIP for Wantage & Grove | Less than £100k | Less than 2 years |
| 3.3 | Liaise with partners to develop new walking, wheeling and cycling schemes to create an easy to navigate, cohesive and safe walking, wheeling and cycling network | Between £100k and £500k | Less than 2 years |
| 3.4 | Investigate changes to the PRoW network to enable use by a wider range of Non-Motorised Users (NMUs) for different journey purposes | Between £100k and £500k | More than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 4.1 | Ensure developments deliver walking, wheeling and cycling provision identified in LCWIPs and SATN | Between £100k and £500k | More than 5 years |
| 4.2 | Ensure developments address any gaps in the provision of walking, wheeling and cycling routes, including connections to existing networks, routes identified in LCWIPs and SATN and between developments | Less than £100k | Up to 5 years |
| 4.3 | Prioritise walking and cycling within developments and ensure that provision integrates with off-site routes | Less than £100k | Up to 5 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 5.1 | Identify opportunities for improvements along and access to waterways and greenways (including the River Thames, disused Wilts and Berks Canal and the Ridgeway) | Less than £100k | Less than 2 years |
| 5.2 | Support the delivery of improvements along and access to waterways and greenways (including the River Thames, disused Wilts and Berks Canal and the Ridgeway) | Less than £100k | Over 2 years |
| 5.3 | Collaborate with partners including the Walk Wheel Cycle Trust and Canal and Riverside Trust to develop wayfinding and signage, help-points, and mapping along waterways and greenways (including the River Thames, disused Wilts and Berks Canal and the Ridgeway), through extending the scope of the Didcot Wayfinding Strategy | Less than £100k | Less than 2 years |
| 5.4 | Explore options with partners to provide place shaping (e.g. pocket parks, outdoor gyms, and other green spaces) along waterways and greenways (including the River Thames, disused Wilts and Berks Canal and the Ridgeway). With this developed alongside, in line with the Didcot Green Infrastructure Strategy | Between £100k and £500k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 6.1 | Explore the reallocation of highway space at the Culham and Clifton Hampden river crossings to improve provision for walking, wheeling and cycling and public transport - subject to the delivery of the Didcot to Culham River Crossing | Between £100k and £500k | Over 2 years |
| 6.2 | Work with partners to remove walking, wheeling and cycling barriers across the Great Western Mainline, Cherwell Valley Line and the Local Road Network | More than £500k | Over 2 years |
| 6.3 | Work with partners and stakeholders to create new links over the River Thames and Cherwell Valley line serving Culham rail station, Culham Campus and strategic sites | Between £100k and £500k | Less than 2 years |
| 6.4 | Work with National Highways to continue developing plans for the Milton Heights walking, wheeling and cycling Bridge | Over £500k | Less than 2 years |
| 6.5 | Work with partners to deliver the Milton Heights walking, wheeling and cycling Bridge | Less than £100k | Over 2 years |
| 6.6 | Explore the opportunities to improve walking, wheeling and cycling across the A34, including connections with Didcot | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 7.1 | Work with partners to create a shared e-scooter and e-bike network, at locations such as mobility hubs, district and community centres, bus stops, leisure. and employment facilities (such as in Didcot and at Harwell Campus, Milton Park, and Culham Campus). | Less than £100k | Less than 2 years |
| 7.2 | Support shared e-scooter and e-bike schemes that link employment sites with residential sites and public transport interchanges | Less than £100k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 8.1 | Review and define the locations for cycle parking, hubs, and hangars including auditing existing locations | Less than £100k | Less than 2 years |
| 8.2 | Work with partners to deliver new, and improve existing, cycle parking. To include the provision for non-standard cycle (e.g. tricycles, cargo bikes, tandems, mobility scooters and adapted bicycles), cycle repair/ maintenance hubs and charging for e-bikes, at appropriate locations. We will also seek to ensure all cycle parking is designed to a high quality so where appropriate, green walls, green roofs, solar panels and landscaping will be provided on and around the cycle parking | Between £100k and £500k | Over 2 years |
| 8.3 | Support the development of a cycle hub at Culham Station | Between £100k and £500k | Over 2 years |
| 8.4 | Develop a cycle parking map showing capacity and levels of use at cycle parking, hubs, and hangars | Between £100k and £500k | Over 5 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 9.1 |
Explore opportunities to provide or improve mobility hubs at major interchanges and along key movement corridors:
|
Between £100k and £500k | Less than 2 years |
| 9.2 | Support the implementation of the Mobility Hub Strategy, including linkage hubs, suburban and rural hubs, and mini hubs | Less than £100k | Over 5 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 10.1 | Work with partners to provide faster bus services, with consideration given to increasing frequencies (including "turn up and go" services) and express, or limited stop services and the optimisation of existing services | Over £500k | Less than 2 years |
| 10.2 | Work with partners to provide new bus services in Science Vale including to places outside Science Vale, to locations that are currently underserved and to new developments | Over £500k | Less than 2 years |
| 10.3 | Work with bus operators to ensure improved reliability, attractiveness and resilience of services | Over £500k | Less than 2 years |
| 10.4 | Work with bus operators to improve the service level in the early morning, and late evenings to support employment and the nighttime economy | Over £500k | Less than 2 years |
| 10.5 | Work with operators to provide long-distance coach services connecting to Science Vale | Over £500k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 11.1 | Work with partners to develop a strategy for the redesign of Didcot Parkway Bus Interchange and Didcot Town Centre, including reviewing routing through the town centre | Between £100k and £500k | More than 2 years |
| 11.2 | Identify opportunities for the improvement of bus infrastructure (e.g. waiting facilities, location for new bus stops, Real Time Information, application of AI, raised kerbs, lighting, shelters, CCTV, onward travel maps). | Over £500k | Up to 5 years |
| 11.3 | Work with partners to develop a strategy for consistent bus branding and route identification across Science Vale. | Less than £100k | Less than 2 years |
| 11.4 | Identify opportunities for bus priority and improvement measures including bus lanes, removal of parking and traffic signal priority within Science Vale | Between £100k and £500k | Up to 5 years |
| 11.5 | Work with partners to introduce bus priority and improvement measures | Over £500k | More than 2 years |
| 11.6 | Work alongside partners to deliver a zero-emission bus network across Science Vale | Over £500k | Up to 5 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 12.1 | Work with Network Rail to ensure the electrification of the rail line between Didcot Parkway and Oxford. | Over £500k | Less than 2 years |
| 12.2 | Work with Network Rail and East West Rail to achieve the extension of East West Rail services to Didcot Parkway and in the future Wantage and Grove, to provide services between Science Vale and Milton Keynes and onwards towards Cambridge | Between £100k and £500k | Less than 2 years |
| 12.3 | Collaborate with partners to improve the accessibility and infrastructure at Culham Rail Station. | Between £100k and £500k | Less than 2 years |
| 12.4 | Work with partners to lobby for additional services and capacity improvements at Didcot Parkway | Between £100k and £500k | Less than 2 years |
| 12.5 | Collaborate with partners to deliver the Strategic Outline Business Case for Wantage and Grove Station | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 13.1 | Work with partners to improve capacity, accessibility, passenger facilities and direct services at Culham | Between £100k and £500k | Over 2 years |
| 13.2 | Support partners to provide the further enhancement of services from Didcot Parkway | Between £100k and £500k | Over 2 years |
| 13.3 | Develop a strategy with Network Rail to support increased freight capacity through Didcot Parkway | Between £100k and £500k | Over 2 years |
| 13.4 | Work with partners to develop a framework to enable the opening of Wantage and Grove Station | Less than £100k | Over 2 years |
| 13.5 | Work with partners to open a station at Wantage and Grove, subject to the Outline Business Case | Over £500k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 14.1 | Collaborate with partners to provide a comprehensive network of car clubs, including the prioritisation of parking for car clubs | More than £500k | Less than 2 years |
| 14.2 | Ensure car clubs use zero emission vehicles, where possible | Less than £100k | Less than 2 years |
| 14.3 | Work with developers and business to provide EV charging and parking to support car clubs/ car share and to encourage/promote car sharing to their employees | Less than £100k | Less than 2 years |
| 14.4 | Develop a car sharing awareness / expansion programme through collaboration with partners | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 15.1 | Identify locations for potential demand management measures in suitable locations including restricting car parking availability | Less than £100k | Less than 2 years |
| 15.2 | Work with partners to develop a strategy for the implementation of demand management measures | Less than £100k | Less than 2 years |
| 15.3 | Support the removal of on-street parking along identified routes and high footfall areas, the LWCIPs, DCC, SATN and priority bus routes and to support the delivery of cycleways, where appropriate | Between £100k and £500k | Over 2 years |
| 15.4 | Consideration for the provision of new or extended Controlled Parking Zones | Between £100k and £500k | Up to 2 years |
| 15.5 | Continue to work with our partners to reduce the number of existing parking spaces at existing employment locations, including but not limited to Milton Park, Harwell Campus, Culham Campus and WilliamsF1 | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 16.1 |
Support the delivery of: a. HIF1 (Widening of the A4130, Didcot Science Bridge, Didcot to Culham River Crossing and Clifton Hampden Bypass). b. Steventon Lights Integrated Transport Scheme. c. Milton Heights walking, wheeling and cycling Bridge. d. Northern Perimeter Road Phase 3. e. Grove Northern Link Road. |
More than £500k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 17.1 |
Consider exploring previously identified potential:
|
More than £500k | Less than 2 years |
| 17.2 |
Explore options for the walking, wheeling and cycling transport schemes safeguarded in the South and Vale JLP:
|
More than £500k | Over 2 years |
| 17.3 |
Consider exploring previously identified potential:
|
More than £500k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 18.1 |
Develop Corridor Movement and Place Strategies on corridors identified in LTCP Part 1: a. A4074. |
Between £100k and £500k | Less than 2 years |
| 18.2 | Consider locations for other Corridor Movement and Place Strategies | Between £100k and £500k | Over 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
|
19.1
|
Continue to collaborate with the district councils to safeguard land within Local Plans for movement schemes | More than £500k | Over 2 years |
| 19.2 | Review whether the safeguarding of land for movement schemes needs to be retained in future Local Plans | Less than £100k | Over 2 years |
| 19.3 | Work to identify new areas where the safeguarding of land would be required for future movement schemes | Less than £100k | Over 2 years |
| 19.4 | Collaborate with partners to explore and identify locations for depots, bus stops and interchanges to support public transport and walking, wheeling and cycling | Less than £100k | Less than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 20.1 | Work with the district councils to continue the electrification of food-waste collection vehicles and encourage all fleet vehicles to be zero-emission (e.g. refuse vehicles, vans). | More than £500k | More than 2 years |
| 20.2 | Explore opportunities to introduce HGV restrictions, for through vehicle trips, in Didcot and Wantage, in areas with high walking, wheeling and cycling movements (e.g. upon delivery of HIF1 and NPR3). | Between £100k and £500k | Less than 2 years |
| 20.3 | Explore opportunities for a zonal network of zero emission parcel deliveries in Didcot, including opportunities for future expansion. | Between £100k and £500k | Less than 2 years |
| 20.4 | Implement a zonal network of zero emission parcel deliveries in Didcot | Between £100k and £500k | Less than 2 years |
| 20.5 | Collaborate with partners to introduce opportunities for first and last mile deliveries hubs using cargo bikes and e-cargo bikes at employment sites in Science Vale | Between £100k and £500k | Less than 2 years |
| 20.6 | Collaborate with partners to explore opportunities to provide micro consolidation hubs at the Science Parks and other multi-operator employment sites | Between £100k and £500k | More than 2 years |
| 20.7 | Support the rollout of parcel/ grocery lockers at key transport locations such as Didcot Parkway, Culham, Wantage and Grove, Mobility Hubs, and local and district centres to support integrated travel | Between £100k and £500k | Less than 2 years |
| 20.8 | Explore the opportunities to deliver rail freight hubs in Science Vale | More than £500k | More than 5 years |
| 20.9 | Investigate the opportunities for a trial of autonomous HGVs and truck platooning in Science Vale, in line with Objective SV22 | Less than £100k | More than 2 years |
| Number | Action | Estimated Cost | Delivery timescale |
| 21.1 | Investigate opportunities to improve flood resilience in areas with the highest risk | Between £100k and £500k | Less than 2 years |
| 21.2 | Support wider use of blue infrastructure for movement schemes, where applicable | Less than £100k | Less than 2 years |
| 21.3 | Support wider use of Sustainable Drainage Systems (SuDS) and at new developments, where applicable | Less than £100k | Less than 2 years |
| 21.4 | Develop a strategy to provide the greening or putting solar panels on of bus stops, train stations, signage, mobility hubs, etc. | Between £100k and £500k | Less than 2 years |
| 21.5 | Support schemes that achieve greening and re-wilding of places | Between £100k and £500k | Ongoing |
| 21.6 | Support schemes and help to implement proposals to reduce air pollution | Between £100k and £500k | Ongoing |
| 21.7 | Support the implementation of projects in the Didcot Green Infrastructure Strategy | Between £100k and £500k | Ongoing |
| Number | Action | Estimated Cost | Delivery timescale |
| 22.1 |
We will seek to explore the following (but not limited to):
SMART infrastructure (combining physical and digital infrastructure). |
Between £100k and £500k | Less than 2 years |
| 22.2 |
In turn we will:
|
Between £100k and £500k | Over 2 years |